Google Halts Belgian Data Centre Work After Authorities Find Unpermitted Building

Exterior of a Google data centre building in Council Bluffs, Iowa (file photo). Photo: Chad Davis / Wikimedia Commons (CC BY 2.0). File photo of a Google data centre in Council Bluffs, Iowa.

Google has halted construction at its data centre site in southern Belgium after regional authorities ordered work to stop, saying the company was building without planning permission. The Walloon Region said inspectors visited the 50-hectare site near Charleroi on Thursday and found a building of 30,000 square metres — three hectares — almost finished, even though the permit change it depended on had been refused in August.

Nicolas Yernaux, spokesman for the Walloon regional authorities, described the work as “a major offence” and said a report was being sent to public prosecutors. About 300 workers were on site when inspectors gave the verbal order to stop. Google later confirmed it had complied. “We have halted works consistent with the direction from local authorities and pending additional guidance,” a Google spokesperson told AFP. “We have operated in Belgium for over 15 years and remain committed to complying with local laws.”

The dispute centres on changes Google sought to the original project. In 2024 the company received a permit for three smaller data centre buildings cooled by air. The following year it asked to merge two of them into a single larger building and to cool it with water drawn from the nearby River Sambre. The Walloon administration approved the amendment in April, but after a citizens’ appeal the regional minister, François Desquesnes, refused it in August, citing the project’s water needs during a drought. Google has challenged that refusal before Belgium’s Council of State, with a hearing set for 7 January.

Environmental group Greenpeace, which had campaigned against the project, said satellite images and drone footage showed construction had continued despite the refusal, and it filed an urgent request with the regional authorities on 25 November. The group argues the site’s water use is unsustainable, pointing to a comparable Google data centre at Saint-Ghislain, near Mons, which it says pumps up to a billion litres of water a year for cooling. Google has not commented publicly on that claim.

The halt is the second time in two months that a European government has stopped work at a Google data centre site, as technology companies race to build the computing capacity behind cloud services and artificial intelligence. The Charleroi project, on a former mining site at Farciennes and Aiseau-Presles, covers about 53 hectares, and Google announced a further one billion euros of investment when construction began. The region says the original 2024 permit remains valid, so Google may still build under those terms — but not under the amended plans.

Sources: Agence France-Presse, “Google halts construction of Belgian data centre on authorities’ order” (https://www.europesays.com/be/50871/); ITdaily, “Walloon Region halts construction of Google data centre in Farciennes” (https://itdaily.com/news/datacenter/google-data-centre-farciennes-halted/), reporting VRT NWS and RTBF.